Some Horizon Europe proposals are drafted before the consortium has established the project logic, partners’ responsibilities and exact topic fit. That is a preventable readiness problem. For calls with 2027 deadlines, agree and record those decisions before opening the template.
What is established about the 2027 calls
The 2027 calls belong to the Horizon Europe Work Programme 2026–2027, which the Commission adopted on 11 December 2025 with a budget of around €14 billion. On 29 September 2026 the Commission amended the 2026–2027 work programmes, adding €500 million and a new work programme part on horizontal activities, which brings the two-year total to around €14.8 billion. These are adopted documents and set the rules for 2027 calls.
Three cautions follow:
- Calls differ. Opening dates, deadlines, type of action, single- or two-stage submission, lump sum funding and specific eligibility conditions are set call by call and topic by topic. The Cluster 4 Industry 2027 calls, for example, have their own published timetable. Always use the relevant current topic page for the opening date and deadline; other 2027 calls follow different calendars.
- Check the current version. After the September amendment, use the topic page on the Funding & Tenders Portal, not a downloaded copy of the work programme from earlier in the year.
- Future programmes are not rules. Proposals for the framework programme that follows Horizon Europe from 2028 are under negotiation. They do not change the conditions of 2027 calls, which run under the current work programme and its General Annexes.
Our overview of what changed in the 2026–2027 work programme covers the programme-level changes. This article is about the decisions a consortium has to make before drafting.
Start with the exact topic
Read the topic page in full and write down, in the consortium’s own words:
- the expected outcomes, which are what the Impact criterion assesses against;
- the scope, including what is explicitly excluded;
- the type of action (RIA, IA, CSA), which determines funding rates and the kind of work expected;
- specific conditions: TRL, required participant types, pilots, links to partnerships or other projects, lump sum, two-stage, blind evaluation, eligibility restrictions;
- the indicative budget per project and the number of projects expected.
If the consortium cannot agree on a one-paragraph description of how its project delivers the expected outcomes within scope, it is not ready to draft.
Decide whether to coordinate or join
Coordination is a role with obligations that run for the whole project, not a status. Before claiming it, check:
- staff capacity for proposal management now and for coordination across the project’s full duration;
- administrative readiness: a validated PIC and LEAR, and the ability to pass a financial capacity check, which in Horizon Europe is normally applied to coordinators requesting EUR 500,000 or more (public bodies and international organisations excepted);
- whether the organisation’s own scientific or technical contribution is central enough to lead.
Joining as a partner with a clearly defined role is often the stronger choice for an organisation new to the programme.
Assess capabilities and missing roles
Map each expected outcome and major task to a named partner and to the evidence that partner can do it. Look in particular for missing expertise, work packages without a credible lead, absent access to users, pilot sites or data where the topic requires them, and no owner for exploitation. Partner names and country coverage alone do not demonstrate delivery capacity.
If the gap is real, decide early whether to strengthen an existing partner’s role, recruit, involve an associated partner or redesign the work. Recruitment is the slowest option. Where a partner is missing, Nexuswelt’s partner search and consortium building starts from a defined role profile.
Design the project logic before the work packages
Agree, in this order: the objectives, the results that will exist at the end, how those results lead to the topic’s expected outcomes, and only then the work packages that produce the results. Writing work packages first tends to produce an administrative division of labour rather than an implementation logic evaluators can follow.
A one-page logic summary, from objectives to results to outcomes, is the most useful document a consortium can produce before drafting. Every section of Part B should be traceable to it.
Establish credible impact and exploitation pathways
The application form asks applicants to name the target groups that would benefit, to describe requirements and potential barriers arising from factors such as regulation, markets and user behaviour, and to propose mitigating measures. It also requires a first version of the plan for dissemination and exploitation, including communication, as an admissibility condition unless the topic says otherwise.
Before drafting, decide who owns each key result, who will use it, what stands in the way, and which partner is responsible for each route to uptake. If no partner can pursue a pathway, it should not be in the proposal.
Confirm preparation capacity and resources
Proposal preparation is unfunded work. Confirm before starting:
- named writers for each section and a single editor responsible for consistency;
- partner input deadlines, including budget figures, effort per work package, researcher details and CVs where required;
- the page limit for your type of action (for standard full proposals, 40 pages for RIA and IA, 45 for lump sum topics, unless the topic says otherwise);
- for lump sum topics, the detailed budget table, which must respect the cost eligibility rules;
- registration in the Participant Register for every participant, the ethics self-assessment and any required declarations;
- time for an independent review before submission.
Work backwards from the verified deadline
Take the deadline from the topic page (deadlines are at 17:00 Brussels time) and plan backwards:
Milestone | Planning note |
Submission | The Portal recommends submitting at least 48 hours before the deadline |
Final partner approval | Allow several working days for internal sign-off |
Independent review and revision | At least one full revision cycle after the review |
Complete first draft | All sections, tables and an approximate budget |
Logic summary and work package structure agreed | Before section-by-section drafting starts |
Go/no-go decision | Recorded, with named coordinator and partners |
The durations depend on the consortium; the sequence does not.
A go/no-go decision table
This table is editorial guidance from Nexuswelt, not an official Commission tool.
Question | Go | Pause or no-go |
Topic fit | Project delivers the expected outcomes within scope | Fit depends on stretching the topic text |
Type of action and TRL | Work matches the action type and any TRL expectation | Maturity is too low or too high for the action |
Specific conditions | All met or achievable before submission | A required participant type or pilot is missing |
Coordinator | Capacity and administrative readiness confirmed | No organisation can carry the role |
Capabilities | Every expected outcome has an owner with evidence | Critical capability missing with no realistic fix |
Impact pathway | Owners, users and barriers identified | No partner can pursue uptake |
Resources | Writers, inputs and review time committed | Drafting depends on goodwill and spare time |
Timeline | Plan fits before the deadline with margin | Plan only works if nothing slips |
Consortium decision checklist
- ☐ Current topic page read in full; conditions recorded
- ☐ One-paragraph project description agreed by all partners
- ☐ Coordinator confirmed, with capacity and administrative readiness
- ☐ Capability map completed; gaps assigned or resolved
- ☐ Logic summary agreed before work packages
- ☐ Owners for key results and uptake routes named
- ☐ Writing team, partner input deadlines and review slot fixed
- ☐ Deadline verified on the Portal and backward plan agreed
Nexuswelt supports consortia through these decisions and the proposal that follows as part of its Horizon Europe support.
Sources
- European Commission: Horizon Europe work programmes
- EU Funding & Tenders Portal
- Horizon Europe Work Programme 2026–2027, General Annexes
- Horizon Europe Standard Application Form, RIA/IA
- European Commission press release IP/26/2004: additional €500 million for Horizon Europe


